In April of 2012 the Plutonium Sustainment program at LANL completed or addressed the following high-level activities: 1) Construction activities on the Low Voltage Electron Beam (LVEB) Welder and Analytical Chemistry gloveboxes have started, successfully closing out MRT L2 Milestone 4195; 2) Completed installation of the Surface Preparation unit in PF4. The unit will be functionally tested in May; 3) Completed casting of the first two near net shape W87 hemishells; 4) Delivered Revision 3 of the Plutonium Sustainment and Manufacturing Study; 5) Completed machining and inspecting the first...